Telecom campuses in the Gulf, colocation retrofits in South-East Asia, micro data centers in European factories and liquid-cooled AI clusters — a selection of deployments where the brief was difficult and the deadline was real.

  • 32 countries
  • 260+ projects
  • Telecom · Colocation · Finance · Industry
Saudi Arabia — 2.4 MW Edge Campus for a National Telecom Operator Saudi Arabia
Telecom 2024 2.4 MW

Saudi Arabia — 2.4 MW Edge Campus for a National Telecom Operator

Twelve 40 ft pods delivered to three regional sites in 22 weeks, each with N+1 UPS and free cooling sized for 48 °C ambient.

2.4 MWTotal IT capacity
22 wksDelivery to handover
1.28Achieved PUE
48 °CDesign ambient
Indonesia — Colocation Hall Retrofit with In-row Cooling Indonesia
Colocation 2023 1.1 MW

Indonesia — Colocation Hall Retrofit with In-row Cooling

A 320-rack hall with uneven heat density was retrofitted row by row, without taking a single customer offline.

1.1 MWCooled capacity
-31%Cooling energy
0Customer outages
1.32PUE after retrofit
Germany — Automotive Plant Micro Data Center Germany
Manufacturing 2024 180 kW

Germany — Automotive Plant Micro Data Center

Three production sites received identical 8-rack pods to run MES and vision systems at the line, replacing ageing server closets.

180 kWIT capacity
3Sites standardised
9 wksPer-site deployment
1.29PUE
Singapore — 1.8 MW Liquid Cooling Deployment for an AI Lab Singapore
AI & HPC 2025 1.8 MW

Singapore — 1.8 MW Liquid Cooling Deployment for an AI Lab

Three containerized CDU units provide N+1 heat rejection for 96 liquid-cooled GPU racks at 45 °C facility water.

1.8 MWHeat rejected
1.14Measured PUE
45 °CFacility water
N+1Pump redundancy
United Arab Emirates — Banking Disaster Recovery Site United Arab Emirates
Finance 2023 600 kW

United Arab Emirates — Banking Disaster Recovery Site

A 600 kW DR facility with 15-minute lithium runtime and fully concurrent maintainability, delivered into an existing shell.

600 kWIT capacity
15 minLithium runtime
2NPower path
6 wksInstallation
South Africa — Off-grid Mining Data Center South Africa
Mining 2022 240 kW

South Africa — Off-grid Mining Data Center

Two 20 ft pods run the mine's control and safety systems on a site with an unreliable grid — and a 1,900 m altitude.

240 kWIT capacity
99.98%Availability
-5 °Cto 42 °C ambient
2Pods deployed

References on request