United Arab Emirates — Banking Disaster Recovery Site

Finance · 2023

United Arab Emirates — Banking Disaster Recovery Site

A 600 kW DR facility with 15-minute lithium runtime and fully concurrent maintainability, delivered into an existing shell.

600 kWInstalled capacity
United Arab EmiratesLocation
2023Handover
FinanceIndustry
600 kW IT capacity
15 min Lithium runtime
2N Power path
6 wks Installation

01 — The challenge

The bank's regulator required a DR site capable of taking core banking traffic within 30 minutes of a primary failure, with no single point of failure in the power path and full maintenance capability while live. The available shell had a floor loading limit that ruled out a conventional VRLA battery room.

02 — The solution

Two 300 kVA HP33 modular UPS frames were installed in a 2N configuration, each paired with an LFP battery cabinet providing 15 minutes at full load. The lithium cabinets weigh roughly 60% of the equivalent lead-acid bank, which kept the installation inside the floor loading limit.

In-row chilled-water units provide N+1 cooling, and every component — UPS module, battery cabinet, cooling unit — can be isolated and replaced while the site remains live.

03 — The result

The site passed the regulator's witness test first time, including a full-load transfer and a live UPS module replacement. Installation took six weeks inside an occupied building, with no disruption to the tenant on the floor below.

United Arab Emirates — Banking Disaster Recovery Site